Construction
The Anglo-Iranian Oil Company commenced the construction of the Kent Refinery, unofficially known as the Grain Refinery, in 1950. The contracts were managed by the Badger Company, with construction carried out by McAlpine and Wimpey.[5]
Pre-construction groundworks were carried out on the southern part of the site, including the infilling of several disused watercourses, namely Wells Fleet, Littlechalk Fleet, and most of Greatchalk Fleet. This work involved the use of one million cubic yards (765,000 m³) of soil, sourced from higher ground to the north of the site.[5][6] To the south-east of the site, the ground level was raised by up to six feet (1.8 m) using compacted sand dredged from the seabed.[5]
Six thousand concrete piles were driven to provide foundations for the major plant and equipment on the marshy ground.[5]
A bay on the Saltpan Reach of the River Medway was enclosed to serve as a storage reservoir for cooling water, filled by the incoming tide. A water channel, three-quarters of a mile (1.2 km) in length (TQ865739 to TQ868749)[7] was constructed to convey water from the reservoir across the site to the refinery pump house, from where it could be distributed around the site for process cooling.[5] The channel had a volumetric capacity of 16 million gallons (73,000 m3). The refinery's cooling water circulation system had a capacity of 3.5 million gallons/hour (15,900 m3/hour).[5]
Initially, five new jetties were constructed on the River Medway, with the capacity to accommodate vessels of up to 32,000 tonnes.[5] A deep-water channel was dredged to enable ships to reach the jetties from the Thames Estuary. This channel, which extended for 4 miles (6.4 km) and was 800 feet (240 m) wide, was excavated to provide a minimum water depth of 28 feet (8.5 m) at low tide.[5]
The initial phase of construction entailed the use of:[5]
At its peak the construction activity on the site employed 8,000 workers; 1,500 were housed in a construction camp at Wallend in the centre of the site.[6][5]
In 1952 the Thames to Grain (T/G) pipeline was recommissioned to carry refined fuel from the BP Kent refinery to the Walton storage depot. The movement of fuel was now in the opposite direction to that originally designed. This led to the need to install new pumping units and to construct a new pump-station at Stoke (TQ851757), located close to the Isle of Grain refinery.[8]
The first phase of construction cost around £40m.[9]
- 37,000 tonnes of concrete
- 119,000 tonnes of steel
- 14 million bricks
- 600 mi of piping